February 1-2

  • BJ+Box proof of concept

February 3

  • (res 1/29) review proof of concept
  • (res 1/29) begin converting sketches to final images
  • (res 1/31) proof of concept complete - Dan
  • (res 1/31) schedule viewing for feedback 3-5 people 2/4-2/10
  • (res 1/31) schedule tank delivery barn
  • schedule electric

February 4

  • Chinese New Year starts (January 25)
  • Joe for barn stairwell enclosure and heater hangers?
  • warmer, melting temps sunny - plastic on barn roof?

February 5 and 6

  • propane heaters scheduled for barn

February 8 - 9

barn propane tank installed

February 10

  • She Box Artists at Artist house
    • She Box Artists at Artist house
      • debrief on feedback
    • Assess workflow and begin Act 2
    • update calendar with new milestones

February 29